CUP: G34H13000620002
AZIONI, ATTIVIT E INTERVENTI FINALIZZATI AL MANTENIMENTO DELL'EFFICIENZA DELLA RETE IDRICA COMUNALE
SUMMARY OF THE PROJECT
AZIONI, ATTIVIT E INTERVENTI FINALIZZATI AL MANTENIMENTO DELL'EFFICIENZA DELLA RETE IDRICA COMUNALE
Implementation indicator
Estensione della rete
- Target
- 4 km
- Achieved
- 4 km
Funding monitored
€ 983,763.37
of which cohesion funds
€ 969,006.92
Given name | Amount |
---|---|
Development and Cohesion Fund | 969006.92 |
Municipality | 14756.45 |
- Economies:
- € 286,046.63
Payments monitored
€ 942,333.54
of which cohesion funds
€ 928,233.14
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2017 | 137439.26 | 137439.26 | 13 |
2018 | 374148.37 | 511587.63 | 52 |
2019 | 239237.54 | 750825.17 | 76 |
2020 | 34242.69 | 785067.86 | 79 |
2021 | 157265.68 | 942333.54 | 95 |
State of progress
Completed
Expected start: 02/03/2017
Effective start: 02/03/2017
Expected end: 28/08/2018
Effective end: 28/08/2018
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI TERMOLI
- Beneficiary
- COMUNE DI TERMOLI
- Executor
- COSTRUZIONI MASTROVINCENZO SAS
At the School of OpenCohesion
OpenCoesione goes to School followed this project in edition 2016-17 with the team “I WATERBOYS” of “ALTRO (SPECIFICARE) "ALFANO DA TERMOLI"” of Termoli, CAMPOBASSO.
Read the Monithon report.
View the creative output.
Read the Monithon report.
View the creative output.
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE MOLISE
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche