CUP: F87D14000020001
FUNIVIA DEL FAITO - ADEGUAMENTO SISMICO E FUNZIONALE E ABBATTIMENTO BARRIERE ARCHITETTONICHE.
Funding monitored
€ 1,636,852.81
of which cohesion funds
€ 1,260,756.20
Given name | Amount |
---|---|
Development and Cohesion Fund | 1260756.20 |
Another public source | 376096.61 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 15/07/2015
Effective start: 02/04/2018
Expected end: 31/12/2016
Effective end: 01/10/2018
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Transport and mobility
- Strade nazionali
Territory
Entities
- Planning body
- ENTE AUTONOMO VOLTURNO SRL
- Implementing body
- ENTE AUTONOMO VOLTURNO SRL
- Beneficiary
- ENTE AUTONOMO VOLTURNO SRL
- Priority QSN
- Reti e collegamenti per la mobilità
- General objective QSN
- Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
- Specific objective QSN
- Contribuire alla realizzazione di un sistema logistico nazionale, supportando la costruzione di una rete nazionale di terminali di trasporto e di logistica, integrata, sicura, interconnessa ed omogenea
Programming area
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Programme
- PROGRAMMA REGIONALE DI ATTUAZIONE (PRA) FSC CAMPANIA
- Line
- Delibera CIPE 62/2011 - Infrastrutture strategiche regionali e interregionali
- Action
- APQ "Sistemi di Mobilità - Atto aggiuntivo"