CUP: G85E18000110002
REALIZZAZIONE COLLETTORI FOGNARI E REALIZZAZIONE DI UN IMPIANTO DI DEPURAZIONE NEL CAPOLUOGO E N.2 FITODEPURATORI NELLA FRAZIONE DI SANTANNA DEL COMUNE DI SEMINARA
SUMMARY OF THE PROJECT
REALIZZAZIONE COLLETTORI FOGNARI E REALIZZAZIONE DI UN IMPIANTO DI DEPURAZIONE NEL CAPOLUOGO E N.2 FITODEPURATORI NELLA FRAZIONE DI SANTANNA DEL COMUNE DI SEMINARA
Implementation indicator
Giornate uomo prestate
- Target
- 5,500 num
- Achieved
- 0 num
Funding monitored
€ 1,105,000.00
of which cohesion funds
€ 1,105,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1105000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 31/12/2020
Effective start: not available
Expected end: 30/06/2021
Effective end: not available
Entities
- Planning body
- REGIONE CALABRIA
- Beneficiary
- COMUNE DI SEMINARA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE CALABRIA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche